The short version
For each payment, start with the contract and the payment cycle. The contract sets the notice route and dates, subject to any term the Act requires the Scheme to supply or replace. The applicable notice identifies the notified sum, the statutory amount for that payment cycle. A valid pay less notice may limit what must be paid now, but it does not change the notified sum. What must be paid by the final date is not necessarily the final value of the work.
On this page
The payment sequence
For each payment cycle, the practical sequence is:
- Payment becomes due under the contract.
- The applicable notice identifies the notified sum.
- A valid pay less notice may limit the immediate amount payable.
- The required amount must be paid by the final date.
- The final contractual value may remain a separate question.
To apply that sequence, identify who gives the notice, each deadline and the final date for payment. Keep the payment due date, payment-notice deadline, pay-less deadline and final date separate. The Scheme supplies or substitutes a term only if, and to the extent, the Act requires it. The applicable territory and contract-date transition also matter.
Which contracts does Part II cover?
In England and Wales, check whether the agreement is a construction contract under section 104 of the Housing Grants, Construction and Regeneration Act 1996 (HGCRA). Then check whether it covers a construction operation under section 105 or a professional service covered by section 104(2), and whether an exclusion or contract-date transition applies. Calling an agreement a construction contract does not establish that the Act covers it. This Guide describes the amended regime for contracts entered into on or after 1 October 2011.
Who gives the payment notice?
For each payment, the contract must provide one of two routes. The payer is the party who must pay; the payee is the party entitled to payment. The contract may name a specified person to give or receive a notice. It may require a notice from the payer or specified person, or from the payee.
Payer or specified-person route
The payer or specified person must give the payee a complying notice no later than five days after the payment due date. The notice states the sum considered due at that date and the basis for it. Check the contract for the notice-giver, recipient and required content.
Payee route
The payee must give the payer or specified person a complying notice no later than five days after the payment due date. It states the sum the payee considers due at that date and the basis. If the contract does not provide a compliant route, the contract and any required Scheme provisions determine what applies. A contract may allow or require an earlier payee notification before the payer-notice deadline. Section 110B(4) treats it as a payee notice for section 110B(2) if it follows the contract and states the expected sum and basis for the due date. The payee cannot give a second section 110B(2) notice for that payment. If the payer or specified person misses the contract’s notice deadline, the payee may give a complying section 110B(2) notice, subject to the earlier-notification rule. The final date for payment of that sum moves later by the number of days between the required payer-notice date and the payee notice.
Is it an application or notice, and which date matters?
A document’s label does not decide whether it is a qualifying application or notice. The contract and objective context determine whether it is an application or notice, rather than a draft, estimate, update or duplicate. The contract, applicable Scheme and payment cycle determine which valuation date, application date or submission or receipt date controls. Assess an early or late application under the relevant route. One tolerated cycle does not establish a universal timing rule or waiver.
What does a pay less notice do?
A pay less notice is separate from a payment notice. It has its own content and timing requirements. It states the sum the payer considers due on the date the notice is served and the basis for that sum. Additional contractual content depends on the notice terms and its function. The notice must meet the contract and section 111(5). If the notified sum comes from a payee notice under section 110A(3) or section 110B(2), the pay less notice cannot come before that reference notice. Other early-service questions depend on the contract and payment cycle. A late payment notice does not automatically become a valid pay less notice. A defective payment notice does not necessarily invalidate a separate pay less notice, but the pay less notice must satisfy its own requirements. It does not repair the payment notice retrospectively.
What makes a notice valid?
The court asks how a reasonable recipient, knowing the relevant contract and context, would understand the document’s function and whether it meets the applicable requirements. The notice must state the relevant sum and its basis clearly enough. No particular title or clause citation is required, but context does not remove a content requirement. A separate calculation can help explain the basis if the notice clearly links to it and a reasonable recipient would understand that link in context. The mere existence of earlier material, or an unclear reference to it, does not incorporate it automatically or cure missing content. Whether the stated sum is right is a different question from whether the notice gives the required sum and basis. Neither a correct amount nor a disputed amount alone settles every question about validity. A notice under section 110A or section 111 may state zero, but it must still follow the applicable route and meet the required content, basis, service and contractual conditions.
What is the notified sum, and what must be paid?
Under section 111(2), the notified sum is the amount in the applicable complying payer or specified-person notice, or payee notice. The payee notice may be given under the contract or section 110B(2). The earlier notification described above is treated as a payee notice under section 110A(3) for this route. A pay less notice does not change which sum is the notified sum. If a compliant pay less notice applies, it limits the immediate payment obligation to the sum it specifies. The notified sum is not necessarily the final contractual value. Subject to any valid pay less notice and the narrow insolvency exception, the payer must pay the notified sum, so far as it has not already been paid, by the final date. Section 111(10) disapplies that obligation only where the contract contains the specified insolvency term and the payee becomes insolvent after the section 111(5)(a) period. This is not a general insolvency, set-off or enforcement rule.
Can the payer still dispute the true value?
The notified sum is the amount identified for the payment cycle; a compliant pay less notice may limit the immediate amount payable. The true-value question is what the work is worth under the contract. Missing a required payment notice can trigger an immediate notified-sum obligation, but it does not make the amount the final contractual value. Once that obligation is met, a true-value adjudication may determine the work’s contractual value. The distinction also does not decide whether a later adjudication concerns the same dispute, what it can decide or the procedural effect of its decision. Those questions depend on the facts, contract and payment cycle.
How the case law developed
In earlier same-application cases, ISG Construction Ltd v Seevic College and Galliford Try Building Ltd v Estura Ltd treated an unchallenged interim value as fixed for that application and adjudication. Grove later rejected the idea that the notified amount became the final contractual value, while preserving the immediate payment obligation. ISG and Estura should not be described as simply overruled or wholly displaced. The Court of Appeal in Grove also concluded that a payer must meet the immediate section 111 obligation before starting a true-value adjudication about that same payment. That payment-first point was technically obiter: the appeal turned on the pay less notice, and Grove records that the respondent was agnostic on timing and offered no reasoned argument. Davenport later described the point as provided after full argument, treated the reasoning as authoritative and followed it; Lidl described Grove as having been addressed in the Court of Appeal with the benefit of submissions from one party. Davenport applied the sequence to a later true-value decision. It did not decide whether an injunction should stop an adjudication begun too early. Lidl held that the rule is not confined to re-valuing the same payment. It can also apply to a later adjudication, including one about defects, delay or a later payment cycle, insofar as it raises matters that could have been the subject of a pay less notice for the particular notified sum. Matters arising only after the relevant pay less notice date may fall outside the rule. Applying that rule, Lidl treated the adjudicator as lacking jurisdiction over the part of the referral that fell within it. Avanton, a stay case, did not decide the jurisdiction submission before it. Lidl nevertheless makes clear that there is no universal bar on adjudication while a notified sum remains unpaid.
Do final payments and final accounts work differently?
Section 111 is not confined to interim payments. But for a final payment, assess the payment route, due date, notice and final-statement terms under the contract. The interim payment-cycle rules do not automatically decide a final-account dispute. Adam Architecture Ltd v Halsbury Homes Ltd addresses the wider reach of section 111. Whether a document is the contractual Final Statement, whether a notice disputes it, and what follows from a termination account depend on the contract and procedural stage. In Oakland Wantage Care Home Ltd v Stepnell Ltd, the court held that a draft or forecast was not the JCT Final Statement. Pre-issue correspondence did not satisfy the clause. That result is specific to those terms and facts; it does not alter the general interim notice rule. Other account authorities remain fact- and contract-specific:
- Harding (t/a M J Harding Contractors) v Paice & Anor — termination-account context; Foundations case note · primary judgment.
- Construction Muzzy Ltd v Davis Construction (South East) Ltd — court declined to decide summarily whether interim applications remained available once the final-account process had begun; primary judgment.
Related issue: suspension
Section 112 gives a right to suspend performance if a sum subject to section 111(1) remains unpaid. At least seven days’ notice of intention stating the grounds is required. This Guide does not explain suspension procedure or tactics. Insolvency, set-off and enforcement are not dealt with here beyond the narrow section 111(10) point above.
Key cases
These six cases are central to the explanation above. Other authorities appear alongside the narrower point they support.
- Henia Investments Inc v Beck Interiors Ltd, [2015] EWHC 2433 (TCC) — notice and application assessment in contractual context; Foundations case note · primary judgment.
- RBH Building Contractors Ltd v Ashley James & Anor, [2026] EWCA Civ 511 — appellate treatment of notice meaning in context; primary judgment.
- S&T (UK) Ltd v Grove Developments Ltd, [2018] EWCA Civ 2448 — notified sum and true value; payment-first reasoning; Foundations case note · primary judgment.
- M Davenport Builders Ltd v Greer & Anor, [2019] EWHC 318 (TCC) — application of sequencing; injunction question left open; Foundations case note · primary judgment.
- Lidl Great Britain Ltd v Closed Circuit Cooling Ltd t/a 3CL, [2023] EWHC 3051 (TCC) — scope of the payment-first rule; jurisdiction over premature referrals; Foundations case note · primary judgment.
- Oakland Wantage Care Home Ltd v Stepnell Ltd, [2026] EWHC 1530 (TCC) — JCT Final Statement result on its specific terms and facts; primary judgment.
Scope and sources
This Guide covers the England-and-Wales payment regime in Part II of the HGCRA. Research is issue-led and includes authorities beyond the Foundations case library. It is a practical overview, not a comprehensive citator; the law may change after the review date above. This Guide is editorial synthesis, not legislation, a judgment or legal advice. Check the contract and primary sources for the payment cycle in question.
Legislation
- Housing Grants, Construction and Regeneration Act 1996, Part II
- Scheme for Construction Contracts (England and Wales) Regulations 1998, Schedule Part II
- Local Democracy, Economic Development and Construction Act 2009, section 149(3)
- England commencement order, SI 2011/1582
- Wales commencement order, WSI 2011/1597
- Scheme amendment for England, SI 2011/2333
- Scheme amendment for Wales, WSI 2011/1715
- Construction Contracts (Exclusion) (Wales) Order 2023, WSI 2023/475